National Budget Agreement in Norway: Millions to the Ofoten Line in the North
The Labour Party government and budget partners have agreed on a national budget deal for 2027. The deal includes necessary funding to begin construction of key project on the Ofoten Line in Northern Norway.
On Wednesday this week, the Labour Party, the Centre Party, the Socialist Left Party and the Red Party reached an agreement for Norway's 2027 national budget following tough budget negotiations.
The budget agreement includes, among other things, new and much-needed funding for the Ofoten Line in Northern Norway, the railway line running from the Port of Narvik to the national border with Sweden.
More specifically, the budget partners have agreed to allocate NOK 52 million to begin construction of the passing track at Søsterbekk on the Ofoten Line.
This project has been identified as the most mature of the planned development projects on the railway line. Formal planning approval has been completed and the project is ready for construction.
With the new funding, construction work now appears set to begin in 2027.
"This allocation of NOK 52 million ensures that work on the Ofoten Line will begin in 2027," says Member of Parliament Bent-Joacim Bentzen (Centre Party) in a press release on the budget agreement.
"The Ofoten Line is crucial for businesses in the north, freight transport and national preparedness, both for Norway and our neighbouring countries. This is why the Centre Party is ensuring that construction of the passing track at Søsterbekk begins in 2027," he adds.
Criticism over lack of funding
The railway line, known as the Ofoten Line on the Norwegian side, runs between Norway and Sweden in the north and continues on the Swedish side as the Iron Ore Line.
The rail corridor is highly important for the transport of iron ore, groceries, seafood and other freight. In addition, it is increasingly regarded as an important artery in the context of Nordic emergency preparedness.
According to the Ofoten Line Alliance, the Ofoten Line makes up one per cent of Norway's railway network, but carries more than 60 per cent of the country's freight volume measured by tonnage.
However, capacity on the railway line is under considerable pressure, while demand and growth on the line continues to increase.
As HNN recently reported, criticism was directed at the lack of funding for new construction projects on the Ofoten Line in the proposed 2027 national budget, presented earlier this autumn.
Speaking to HNN, Port Director Børge Edvardsen Klingan at Narvik Port, warned of overstretched capacity and weakened preparedness.
“This is a low-cost, but important measure,” he elaborated on the project at Søsterbekk, adding:
"Once completed, a passing track at Søsterbekk will allow for three additional trains in each direction. It will be a major and important contribution toward further increasing capacity in the long term," he explained.
Broad agreement
Several parties have recently presented their alternative national budgets, in which funding for the Ofoten Line has been included and prioritised.
The Centre Party, a budget partner, proposed NOK 52 million to start construction of the Søsterbekk passing loop. The Socialist Left Party proposed NOK 160 million for the Ofoten Line. The Red Party allocated NOK 120 million in start-up funding for new passing loops.
In addition, the Liberal Party proposed NOK 200 million, while the Conservative Party included NOK 120 million in its alternative budget.
The cost of completing the Søsterbekk passing track project is estimated at around NOK 160 million.